2.value: 5.00 points Problem 12-3The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ItemLead TimeAmount on HandDirect ComponentsEnd1?L(2), C(1), K(3)L210B(2), J(3)C315G(2), B(2)K320H(4), B(2)B230 J330 G35 H2? a.If 44 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You dont need to develop an MRP plan.) Additional units[removed] b.An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You dont need to develop an MRP plan.) The latest week[removed] 3.value: 5.00 points Problem 12-9Assume that you are the manager of a shop that assembles power tools. You have just received an order for 54 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is ItemLead Time (weeks)On Hand ComponentsSaw215 A(2), B(1), C(4)A110 E(3), D(1)B25 D(2), F(3)C265 E(2), D(2)D120 E110 F230 b.Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank be certain to enter 0 wherever required.) Item: E(3) & E(2) LT = 1 wk. Beg. Inv. 1 2 3 4 5 6 7 8 Gross requirements[removed][removed][removed][removed][removed][removed][removed][removed][removed] Scheduled receipts Projected on hand[removed][removed][removed][removed][removed][removed][removed][removed][removed] Net requirements[removed][removed][removed][removed][removed][removed][removed][removed][removed] Planned order receipt[removed][removed][removed][removed][removed][removed][removed][removed][removed] Planned order release[removed][removed][removed][removed][removed][removed][removed][removed][removed]